Construction Draw Request Review
Before you approve a contractor's pay application, check the math, compare % billed with what's actually built, confirm retainage and change orders, and list missing lien waivers. You get approve, approve a reduced amount, or hold.
- 1Copy the prompt
- 2Fill the highlighted brackets
- 3Paste into ChatGPT
The prompt
## Your role
You're an owner's construction draw reviewer, the careful kind lenders and owners hire so they don't pay ahead of the work. You check every line of the pay application, compare it with what's in place on site, and give me a clear recommendation with the math shown.
## First, ask me (one message)
1. Project basics: what's being built, original contract sum, approved change orders (number and amount), and any pending change orders.
2. The pay application for this draw: the summary page and the line-by-line continuation sheet (schedule of values), or the contractor's own format. A PDF, photo or spreadsheet is fine.
3. Retainage terms: the % held, and whether it drops at a milestone (for example, at 50% complete).
4. What I've already paid on earlier draws.
5. The construction budget and contingency, and my lender's draw rules if there's a loan.
6. Evidence of progress: the inspector's or lender's site report with % complete by line, or dated site photos.
7. Stored materials claimed this period, and the invoices for them.
8. Lien waivers I have: from the contractor and from subs and suppliers, conditional or unconditional, and for which draws.
9. My state (lien waiver rules and forms differ by state).
## Then check, in this order
1. **Math.** For each line: scheduled value, previous work, this period, stored materials, total to date, % complete, balance to finish, retainage. Recompute the totals. Then: total completed and stored − retainage − previous payments = amount due now. Flag any mismatch.
2. **Billed vs built.** Compare % billed with the inspector's % or the photos, line by line. Flag lines billed ahead of the work, any line over 100%, and early-loaded items like general conditions or mobilization.
3. **Change orders.** Only approved change orders should be billed. Flag pending ones.
4. **Retainage.** Is the right amount held this period, and was any reduction actually earned?
5. **Stored materials.** Are there invoices, proof of insurance, and a secure location?
6. **Lien waivers.** Conditional waivers for this draw and unconditional waivers for the last one, from the contractor and every sub or supplier paid with it. List what's missing by name.
7. **In balance?** Does the remaining budget, including contingency, still cover the balance to finish? Compare contingency used with % complete.
## Output format (always this)
**Recommendation:** APPROVE $X, APPROVE REDUCED $Y, or HOLD, with the one reason that drives it.
| Line | Scheduled value | % billed | % in place | Over-billed $ | Note |
|---|---|---|---|---|---|
**Math check:** completed and stored $A − retainage $B − previous payments $C = due now $D (as billed vs as recommended).
**Missing before payment:** documents and waivers, by name.
**Questions for the contractor:** up to 5, polite and specific.
**Budget health:** remaining budget vs balance to finish, contingency used vs % complete.
## Rules
- Use only the documents and numbers I give you. Label anything you estimate.
- Flag and ask; don't accuse. A line billed ahead of the inspector may have a good reason.
- Don't pay ahead of the work: if % billed is higher than % in place, recommend the lower number until it's explained.
- Lien law is state-specific. Tell me to confirm waiver forms and timing with my lender, title company or construction attorney. This is not legal or financial advice.The rest of this prompt is locked
ChatGPT can read a pay application PDF or photo and recompute every line in code, and OpenAI's newest model (GPT-6.1 Terra, Oct 26 2026) is built for reading forms and documents. Claude is a strong choice for long contracts and the written questions.
- Also works in
- Claude, Gemini
- Activity
- Analyze
- Level
- Advanced
See an example output
Illustrative example only, made up to show the format. Your results will depend on your inputs and the model.
ILLUSTRATIVE EXAMPLE (made-up project) Contract $1,200,000, draw 4, retainage 10%, previous payments $468,000. Recommendation: APPROVE REDUCED $58,500 (billed $82,800). Framing is billed ahead of the work. | Line | Scheduled value | % billed | % in place | Over-billed $ | Note | |---|---|---|---|---|---| | Framing | $180,000 | 85% | 70% | $27,000 | Inspector shows roof framing not started | | Plumbing rough-in | $64,000 | 50% | 50% | $0 | Matches | | General conditions | $96,000 | 45% | n/a | Ask | Project is about 38% complete | Math check: as billed $612,000 − $61,200 retainage − $468,000 = $82,800 due. As recommended $585,000 − $58,500 − $468,000 = $58,500 due. Missing before payment: unconditional waiver from the framing sub for draw 3; conditional waivers for draw 4 from the plumbing and electrical subs. Questions for the contractor: 1) Can you share photos of the framing billed this period? 2) Why are general conditions ahead of overall progress?
Turn it into a bot
- Each time a pay application comes in, paste it with the inspector's report and the waivers you have.
- Send the contractor the questions, then rerun the prompt with their answers before you approve.
- Pair it with Construction Budget Builder to set up the budget and Pro Forma Sanity Check when costs change the deal.
Questions
What is retainage in a construction draw?
A percentage of each payment (often 5% to 10%) that the owner holds back until the work is finished, to make sure punch-list items and closeout get done. Your contract sets the percentage and any reduction.
Why do lien waivers matter before I pay?
If a sub or supplier isn't paid, they may be able to file a lien on your property even though you paid the contractor. Collecting the right waivers with each draw helps protect you. Rules differ by state.
Which AI tool is best for Construction Draw Request Review?
ChatGPT. ChatGPT can read a pay application PDF or photo and recompute every line in code, and OpenAI's newest model (GPT-6.1 Terra, Oct 26 2026) is built for reading forms and documents. Claude is a strong choice for long contracts and the written questions. It also works in Claude, Gemini.
Is the Construction Draw Request Review prompt free?
Yes. Copy it for free, replace the highlighted [BRACKETS] with your details, and paste it into ChatGPT or another AI chat. The example output on this page is made up to show the format, not a real result.
Pairs well with this prompt
Construction Budget Builder
Build a line-item construction budget by CSI division with a contingency and draw schedule.
Real EstatePlanPro Forma Sanity Check
Stress-test a development pro forma and surface the assumptions most likely to sink the deal.
Real EstateAnalyzeSpec Home Margin Stress Test
Before you build a spec home, see how much of a price cut, a slow sale or a cost overrun your margin can survive, and compare two price points side by side. Inspired by Shelby and Dennis of Story Builders on The Wisdom We Borrow.
Real EstateAnalyzeMore in Real Estate Development
See all 7Lender Pitch Deck Writer
Draft a concise, lender-ready deal package and slide outline for a construction loan.
Real EstateBuild / CreatePermit Timeline Planner
Map every approval step and realistic durations from land closing to certificate of occupancy.
Real EstatePlanZoning in Plain English
Turn a dense zoning code section into a clear summary of what you can actually build.
Real EstateLearnOther ways to analyze with AI
Offer Price From Comps
Turn a list of sold land comps into a defensible market value and offer range.
LandAnalyzeParcel Due Diligence Checklist
Get a parcel-specific due diligence checklist with where to verify each item.
LandAnalyzeSeller-Finance Terms Calculator
Design owner-financing terms and an amortization schedule that hits your return target.
LandAnalyze